Rural MV/LV Distribution Grid Overhaul
Transmission Lines
Back to Project Portfolio & Missions

Rural MV/LV Distribution Grid Overhaul

Complete reconstruction of rural power grids across three villages featuring 107 concrete poles and 11 km aerial bundled cable.

Project Overview

Overhauling medium and low-voltage electrical lines across three rural communities, replacing bare aluminum wires with modern aerial bundled cables to reduce transmission losses.

Technical Execution

  • Placement of 107 concrete utility poles and 2 steel light structures
  • Mounting and activation of 5 distribution transformers (25 & 50 kVAR) with custom panels
  • Stringing of 11 kilometers of aerial bundled cables (ABC)
  • Delivered 7 days ahead of contracted schedule